Lesson 10 · Production & IE

SMV — the standard minute value

7 min

In a real company

Industrial engineer (IE), work-study officer, production planner

SMV is the time a trained operator needs for an operation at a normal pace, including allowances. Line planning, CMT costing, targets and incentives all start from SMV.

Key ideas

  • Time-study the operation several times and take the average observed time.
  • Rate the operator's pace (100% = standard). Basic time = observed × rating.
  • Add allowances for personal needs, fatigue and delays (PF&D, often 12–18%).
  • Output per hour = 60 ÷ SMV × efficiency.

Formula

Basic time
= Observed time × Rating%
SMV
= Basic time × (1 + Allowance%)
Output / hour
= 60 ÷ SMV × Efficiency%

Worked example

Collar attach: average observed time 42 seconds, operator rated at 90%, allowances 15%, line efficiency 70%.

  1. 1Observed = 42 ÷ 60 = 0.70 min
  2. 2Basic = 0.70 × 0.90 = 0.63 min
  3. 3SMV = 0.63 × 1.15 = 0.7245 min
  4. 4Output = 60 ÷ 0.7245 × 0.70 = 58 pcs/hour

✅ SMV 0.72 min; about 58 collars per hour per operator.

Try it live in the calculator

Common mistakes

  • Timing a single cycle — always average several.
  • Skipping the rating step.
  • Forgetting allowances, which makes targets impossible.

Quick quiz

Answer 2 of 3 correctly to complete the lesson.

  1. 1. Observed 0.80 min, rating 100%, allowance 10%. SMV?

  2. 2. SMV 0.5 at 100% efficiency — output per hour?

  3. 3. PF&D allowance stands for…