Lesson 11 · Production & IE

Line efficiency

5 min

In a real company

Production manager, IE, line supervisor

Efficiency shows how much of the paid time was converted into standard minutes of output. It is reported for every line every day and drives the factory's cost per minute.

Key ideas

  • Produced minutes = output × SMV.
  • Available minutes = operators × hours × 60.
  • Efficiency = produced ÷ available × 100.

Formula

Produced minutes
= Output × SMV
Available minutes
= Operators × Hours × 60
Efficiency %
= Produced ÷ Available × 100

Worked example

A 40-operator line made 560 shirts (SMV 22) in an 8-hour day.

  1. 1Produced = 560 × 22 = 12,320 min
  2. 2Available = 40 × 8 × 60 = 19,200 min
  3. 3Efficiency = 12,320 ÷ 19,200 = 64.17%

✅ 64.17% line efficiency.

Try it live in the calculator

Common mistakes

  • Counting helpers differently every day.
  • Using the wrong SMV (sample vs bulk).
  • Ignoring overtime hours in available minutes.

Quick quiz

Answer 2 of 3 correctly to complete the lesson.

  1. 1. Output 300, SMV 20, 25 operators × 8 h. Efficiency?

  2. 2. Available minutes for 30 operators × 9 hours?

  3. 3. If efficiency goes up, the real cost per minute…